EXAMPLEIllustrative example · fictional restaurant «Sazón de Origen». Not your data: your result is built with YOUR restaurant's.See the assistant →
Sazón de OrigenFictional contemporary Colombian restaurant in Medellín, 2 locations, 6 years in business. Every sample result in the library comes from this same case.
General Management and Strategy

Sample result

Project Roadmap Builder for Restaurants

The owner asked this:«I have nine projects written down from the last two years. Tell me which goes first, which can run in parallel and which is not due yet.»

① The nine, split into projects and wishes

What the owner wrote downProject or wish?Written precondition
Standard recipes and costing for the menuProjectNone. It is the precondition for almost everything else
Own delivery with an appProjectCosting closed: packaging changes the margin per plate
Weekday breakfastsProjectA shift grid and an owner other than the owner
Virtual brand for sancochosProjectCosting plus kitchen capacity measured at peak
Kitchen certificationProjectWritten procedures, which come out of the same costing work
Wine listLight projectNone. It fits in parallel
Third locationProject, not yetLocation 2 standardized and food cost per plate under the method's ceiling
FranchiseA vague wish todayTwo locations with the same result 8 weeks running
"Modernize the image"Vague wishNo definable result: it gets reframed or leaves the route

Two of the nine are not projects: they have no definable result. Leaving them floating on the list is what makes nine pending items feel like twenty.

② The 60-week route, one anchor per stage

StageAnchor projectDepends onExit milestone (threshold, 8-week window)InvestmentOwner
S1 · wk 1-12Standard recipes and costing for the 12 highest-volume items—Food cost on those 12 under the method's per-plate ceiling, 8 weeks running4,200,000Head chef
S2 · wk 13-24Own delivery with an appS1Margin per own order above the delivery platform's, 8 weeks18,000,000Owner
S3 · wk 25-36Weekday breakfasts at location 1S140 covers a day on average and contribution margin above 38%, 8 weeks9,500,000Location 1 manager
S4 · wk 37-48Virtual sancocho brand out of the location 2 kitchenS1, S225 orders a day without touching dining-room ticket times, 8 weeks11,000,000Location 2 shift lead
S5 · wk 49-60Compared standardization of both locationsS1 to S4Same food cost and same incident rate at both, 8 weeks3,000,000Owner

Light parallels: wine list inside S2, kitchen certification inside S3. Nothing else: two anchors in one stage is a badly split stage.

Hours test against the 24 people: S2 asks 6 weekly hours of the owner and the wine list another 1.5; that is 7.5 of the 8 available. It squeaks through, which is exactly why certification cannot be pulled ahead of S2. The head chef sits at 5 of his 6 hours during S1.

The full example has 1 more part(s): you see them inside the library, with your account.